[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-979342":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},979342,707,1,"单选题","某工程按下表要求组织流水施工，相应流水步距KⅠ-Ⅱ及KⅡ-Ⅲ分别应为多少天？",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2,2",false,{"key":16,"text":17,"correct":14},"B","2,3",{"key":19,"text":20,"correct":14},"C","3,3",{"key":22,"text":23,"correct":24},"D","5,2",true,"提示:该工程组织为非节奏流水施工，相应流水步距KⅠ-Ⅱ及KⅡ-Ⅲ应按“累加错位相减取大值”的方法计算。\\ 累加系列： 取大值后:KⅠ-Ⅱ=5，KⅡ-Ⅲ=2。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业基础知识","建筑工程",0]