[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-979340":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},979340,707,1,"单选题","某二层楼进行固定节拍专业流水施工，每层施工段数为3，施工过程有3个，流水节拍为2d，流水工期为：",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","16d",true,{"key":16,"text":17,"correct":18},"B","10d",false,{"key":20,"text":21,"correct":18},"C","12d",{"key":23,"text":24,"correct":18},"D","8d","提示：固定节拍专业流水施工工期计算公式：流水工期= (m+n-1)t= (3X2+3-1) X 2=16d。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业基础知识","建筑工程",0]