[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-979339":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},979339,707,1,"单选题","下列哪项不属于确定流水步距的基本要求？",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","始终保持两个施工过程的先后工艺顺序",false,{"key":16,"text":17,"correct":14},"B","保持各施工过程的连续作业",{"key":19,"text":20,"correct":21},"C","始终保持各工作面不空闲",true,{"key":23,"text":24,"correct":14},"D","使前后两施工过程施工时间有最大搭接","提示:确定流水步距应考虑始终保持两个施工过程的先后工艺顺序、保持各施工过程的连续作业、使前后两施工过程施工时间有最大搭接，但是，允许有工作面空闲。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业基础知识","建筑工程",0]