[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-979338":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},979338,707,1,"单选题","在施工段的划分中，下列中哪项要求是不正确？",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工段的分界同施工对象的结构界限尽量一致",false,{"key":16,"text":17,"correct":14},"B","各施工段上所消耗的劳动量尽量相近",{"key":19,"text":20,"correct":14},"C","要有足够的工作面",{"key":22,"text":23,"correct":24},"D","分层又分段时，每层施工段数应少于施工过程数",true,"提示:在施工段的划分中，要求施工段的分界同施工对象的结构界限尽量一致，各施工段上所消耗的劳动量尽量相近，施工段上要有足够的工作面；分层又分段时，每层施工段数应大于或等于施工过程数，少于施工过程数是不正确的。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业基础知识","建筑工程",0]