[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-979333":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},979333,707,1,"单选题","在安排各施工过程的施工顺序时，可以不考虑下列中的哪一项？",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工工艺的要求",false,{"key":16,"text":17,"correct":14},"B","施工组织的要求",{"key":19,"text":20,"correct":14},"C","施工质量的要求",{"key":22,"text":23,"correct":24},"D","施工人员数量的要求.",true,"",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业基础知识","建筑工程",0]