[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-979330":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},979330,707,1,"单选题","下列中哪一项不是评价单位工程施工进度计划质量的指标？",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工期",false,{"key":16,"text":17,"correct":14},"B","资源消耗的均衡性",{"key":19,"text":20,"correct":14},"C","主要施工机械的利用率",{"key":22,"text":23,"correct":24},"D","劳动消耗量",true,"提示:劳动消耗量反映劳动力耗用情况，与单位工程施工进度计划质量的评价关系不大。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业基础知识","建筑工程",0]