[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-979323":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},979323,707,1,"单选题","砌砖工程采用铺装法砌筑和施工期间气温超过30°C时，铺浆长度分别不得超过多少？",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","700mm,500mm",false,{"key":16,"text":17,"correct":18},"B","750mm, 500mm",true,{"key":20,"text":21,"correct":14},"C","500mm,300mm",{"key":23,"text":24,"correct":14},"D","600mm,400mm","提示:依据《砲体工程施工质量验收规范》(GB 50203-2002)中第5. 1. 5条规定，砌砖工程采用铺浆法砌筑时，铺浆长度不得超过750mm；施工期间气温超过30°C时，铺浆长度不得超过 500mm。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业基础知识","建筑工程",0]