[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-979307":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},979307,707,1,"单选题","关于砖墙施工工艺顺序，下面所述哪个正确？",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","放线-抄平-立皮数杆-砌砖-清理",false,{"key":16,"text":17,"correct":14},"B","抄平-放线-立皮数杆-砌砖-清理",{"key":19,"text":20,"correct":21},"C","抄平-放线-摆砖样-立皮数杆-砌砖-清理",true,{"key":23,"text":24,"correct":14},"D","抄平-放线-立皮数摆砖样-砌砖-清理","提示:按照砖嬙的施工工艺过程，应首先抄平、放线，然后摆砖样，即按选定的组砌方式摆第一皮砖，然后在各转角部位立皮数杆，挂线砌筑，最后清理。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业基础知识","建筑工程",0]