[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-979294":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},979294,707,1,"单选题","结构构件的吊装过程一般为：",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","绑扎、起吊、对位、临时固定、校正和最后固定",true,{"key":16,"text":17,"correct":18},"B","绑扎、起吊、临时固定、对位、校正和最后固定",false,{"key":20,"text":21,"correct":18},"C","绑扎、起吊、对位、校正、临时固定和最后固定",{"key":23,"text":24,"correct":18},"D","绑扎、起吊、校正、对位、临时固定和最后固定","提示:结构构件的吊装过程一般为绑扎、起吊、对位、临时固定、校正和最后固定。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业基础知识","建筑工程",0]