[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-979280":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},979280,707,1,"单选题","在滑升模板提升的过程中，将全部荷载传递到浇筑的混凝土结构上是靠什么设备？",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","提升架",false,{"key":16,"text":17,"correct":18},"B","支承杆",true,{"key":20,"text":21,"correct":14},"C","千斤顶",{"key":23,"text":24,"correct":14},"D","操作平台","提示:滑升模板系统的全部荷载，最终是靠支承杆传递到混凝土结构上的。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业基础知识","建筑工程",0]