[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-979248":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},979248,707,1,"单选题","关于梁模板拆除的一般顺序，下面所述哪个正确？ Ⅰ.先支的先拆，后支的后拆 Ⅱ.先支的后拆，后支的先拆 Ⅲ.先拆除承重部分，后拆除非承重部分 Ⅳ.先拆除非承重部分，后拆除承重部分.",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Ⅰ、Ⅲ",false,{"key":16,"text":17,"correct":18},"B","Ⅱ、Ⅳ",true,{"key":20,"text":21,"correct":14},"C","Ⅰ、Ⅳ",{"key":23,"text":24,"correct":14},"D","Ⅱ、Ⅲ","提示:根据模板的施工工艺，拆模的顺序与支模的顺序相反，先支的后拆，后支的先拆。承重部位的模板，必须待结构混凝土达到一定强度后方可拆除，故先拆除非承重部分，后拆除承重部分。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业基础知识","建筑工程",0]