[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-978857":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},978857,706,1,"单选题","某砂土场中的一钻孔在15m处进行重型动力触探试验，贯入18cm,锤击数为30击， 触探杆在地面以上长度为1.5m，地下水位2.0m，修正后的锤击数为（ ）击。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","9.5",false,{"key":16,"text":17,"correct":14},"B","11.3",{"key":19,"text":20,"correct":21},"C","13.3",true,{"key":23,"text":24,"correct":14},"D","13.5","根据《岩土工程勘察规范》（GB 50021-2001）（2009年版）附录B第B. 0. 1条计算，杆长修正为：L= 15+ 1.5 =16. 5m， 查表经插值后得修正系数α=0.668，N′63.5=0. 668 ×16. 67 =11.14；地下水修正为：N63.5=1.1N′63.5 + 1 =1. 1×11. 14 + 1 =13.25（击）。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业案例","建筑工程",0]