[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-978577":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},978577,706,1,"单选题","某基坑潜水含水层厚度为20m，含水层渗透系数k=4m\u002Fd，平均单井出水量Q=500m3\u002Fd。井群的引用影响半径R0= 130m。井群布置如图7-15所示，试按行业标准《建筑基坑支护技术规程》（JGJ 120—1999）计算该基坑中心点水位降深 S最接近（ ）m。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1.5",false,{"key":16,"text":17,"correct":14},"B","4.4",{"key":19,"text":20,"correct":14},"C","5.3",{"key":22,"text":23,"correct":24},"D","9.0",true,"根据《建筑基坑支护技术规程》（JGJ 120—1999）第8. 3. 7条，当为潜水完整井稳定流时，基坑中心点水位降深为： 式中，S为在基坑中心处或各井点中心处地下水位降深；r1,r2,…，rn为各井距基坑中心或各井中心处的距离。",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业案例","建筑工程",0]