[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-978573":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},978573,706,1,"单选题","在饱和软黏土地基中开挖条形基坑，采用8m长的板桩支护，如图7-13所示。地下水位已降至板桩底部，坑边地面无荷载，地基土重度为y=19kN\u002Fm3，通过十字板现场测试得地基土的抗剪强度为30kPa,按《建筑地基基础设计规范》（GB 50007—2002）规定，为满足基坑抗隆起稳定性要求，此基坑最大开挖深度不能超过（ ）m。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1.2",false,{"key":16,"text":17,"correct":18},"B","3.3",true,{"key":20,"text":21,"correct":14},"C","6. 1",{"key":23,"text":24,"correct":14},"D","8.5","",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业案例","建筑工程",0]