[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-978479":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},978479,706,1,"单选题","某一办公楼，楼长46.0m,宽12.8m，总建筑面积2860m2。地基土为杂填土，地基承载力特征值fa=86kPa。拟采用灰土挤密桩，设计桩径d=400mm，桩内填料的最大干密度为ρdmax= 1.67t\u002Fm3 ；场地处理前平均干密度为 =1. 33t\u002Fm3，挤密后桩土间平均干密度要求达到 = 1.54t\u002Fm3，进行灰土挤密桩设计。 (1)桩孔按等边三角形布置，桩孔之间的中心距离最合适的是（ ）m。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.60",false,{"key":16,"text":17,"correct":14},"B","0.80",{"key":19,"text":20,"correct":21},"C","1.00",true,{"key":23,"text":24,"correct":14},"D","1.20","根据《建筑地基处理技术规范》（JGJ 79—2002）第14. 2. 3条，桩孔之间的中心距离的计算公式为：",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业案例","建筑工程",0]