[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-978470":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},978470,706,1,"单选题","如图5-6所示，某场地中淤泥质黏土厚15m,下为不透水土层，该淤泥质黏土层固结系数Ch=CV=2.0×10-3cm2\u002Fs，拟采用大面积堆载预压法加固，采用袋装砂井排水，井径为dw=70mm,砂井按等边三角形布置，井距l= 1.4m，井深度15m，预压荷载p=60kPa；一次匀速施加，时间为12天，开始加载后100天，平均固结度接近下列()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0.80",false,{"key":16,"text":17,"correct":14},"B","0.85",{"key":19,"text":20,"correct":14},"C","0.90",{"key":22,"text":23,"correct":24},"D","0. 95",true,"根据《建筑地基处理技术规范》（JGJ 79—2002）第5. 2. 4条、第5. 2. 5条和第 5. 2. 7 条，有效排水直径de=1. 05l= 1. 05×1.4 = 1.47m；井径比n= de\u002Fdw = 1.47\u002F0.07 = 21；砂井穿透受压土层α，β值分别为：",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业案例","建筑工程",0]