[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-978445":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},978445,706,1,"单选题","某地基软黏土层厚18m，其下为砂层。土的水平向固结系数为ch=3.0×10-3cm\u002Fs2。现采用预压法固结，砂井做为竖向排水通道打穿至砂层，砂井直径为dw=0.3m，井距2.8m，按等边三角形布置，预压荷载为120kPa，在大面积预压荷载作用下按《建筑地基处理技术规范》(JGJ 79—2002)计算，预压150天时地基达到的固结度（为简化计算，不计竖向固结度）最接近（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.95",false,{"key":16,"text":17,"correct":18},"B","0. 90",true,{"key":20,"text":21,"correct":14},"C","0.85",{"key":23,"text":24,"correct":14},"D","0. 80","",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业案例","建筑工程",0]