[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-978261":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},978261,706,1,"单选题","某地泥石流调查资料：固体物质体积与水的体积比为0.28，固体物质比重为2.65，设计清水流量为600m3\u002Fs，补给区中固体物质的原始含水量为38%,按第一种配方法计算泥石流设计流量为（ ）m3\u002Fs。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","600",false,{"key":16,"text":17,"correct":14},"B","680",{"key":19,"text":20,"correct":21},"C","792",true,{"key":23,"text":24,"correct":14},"D","880","泥石流设计流量的具体计算如下：",{"id":6,"name":27,"category":28,"favorite":29},"岩土专业案例","建筑工程",0]