[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-976783":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},976783,705,1,"单选题","某项目第1、2年年初分别投资800万元、400万元，第3年开始每年年末净收益300万元，项目运营期8年，残值30万元。设折现率为10%，已知(P\u002FF,10%,1)=0.9091、 (P\u002FF, 10%,2) = 0. 8264、(P\u002FF,10%,10)=0. 3855、(P\u002FA,10%,8) = 5. 3349。则该项目的财务净现值为：",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","158. 99 万元",false,{"key":16,"text":17,"correct":18},"B","170. 55 万元",true,{"key":20,"text":21,"correct":14},"C","448. 40 万元",{"key":23,"text":24,"correct":14},"D","1230 万元","提示：可先绘出现金流量图再计算。P=-800-400(P\u002FF,10%,1)+300(P\u002FA,10%,8) (P\u002FF, 10%,2) + 30(P\u002FF, 10%, 10) =170. 55。",{"id":6,"name":27,"category":28,"favorite":29},"岩土基础知识","建筑工程",0]