[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-966904":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},966904,701,3,"判断题","灭火剂输送管道经水压强度试验合格后还应进行气密性试验，经气压强度试照合格可不进行气密性试验。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"灭火剂输送管道经水压强度试验合格后还应进行气密性试验，经气压强度试照合格且在试验后未拆卸过的管道可不进行气密性试验。",{"id":6,"name":21,"category":22,"favorite":23},"高级技能","建筑工程",0]