[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-966175":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},966175,701,3,"判断题","干式系统水流报警装置应每月试验一次，试验时打开报警试验阀，一部分水流将进入压力开关和\u002F或水力警铃，检查合格后，关闭报警试验阀。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"干式系统水流报警装置应每季度试验一次，试验时打开报警试验阀，一部分水流将进入压力开关和\u002F或水力警铃，检查合格后，关闭报警试验阀。",{"id":6,"name":21,"category":22,"favorite":23},"高级技能","建筑工程",0]