[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-965145":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},965145,701,1,"单选题","下列消防炮的安装与施工不符合要求的有：（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","与消防炮连接的电、液、气管线应安装牢固，且不得干涉回转机构。",false,{"key":16,"text":17,"correct":14},"B","消防炮安装应符合设计要求，且应在供水管线系统试压、冲洗合格后进行。",{"key":19,"text":20,"correct":21},"C","消防炮回转范围应与回转机构相对应",true,{"key":23,"text":24,"correct":14},"D","消防炮安装后，应检查确认在其设计规定的水平和俯仰回转范围内不与周围的构件碰撞","消防炮的安装与施工要求： （1）消防炮安装应符合设计要求，且应在供水管线系统试压、冲洗合格后进行。 （2）消防炮安装前应确定基座上供灭火剂的立管固定可靠。 （3）消防炮回转范围应与防护区相对应。 （4）消防炮安装后，应检查确认在其设计规定的水平和俯仰回转范围内不与周围的构件碰撞。 （5）与消防炮连接的电、液、气管线应安装牢固，且不得干涉回转机构。",{"id":6,"name":27,"category":28,"favorite":29},"高级技能","建筑工程",0]