[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-965024":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},965024,701,1,"单选题","按照相关消防设计规范要求对建筑物进行灭火配置验收，项目缺陷划分为严重缺陷项 A、重缺陷项B和轻缺陷项C。下列灭火器配置验收合格的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","A=0，B=1，C=4",false,{"key":16,"text":17,"correct":18},"B","A=0，B=1，C=3",true,{"key":20,"text":21,"correct":14},"C","A=0，B=2，C=2",{"key":23,"text":24,"correct":14},"D","A=0，B=2，C=3","《建筑灭火器配置验收及检查规范》GB50444-2008对建筑物进行灭火器配置验收，项目缺陷划分为严重缺陷项A、重缺陷项B和轻缺陷项C。灭火器配置验收台格的标准是A=0，B=1，C=3",{"id":6,"name":27,"category":28,"favorite":29},"高级技能","建筑工程",0]