[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-962786":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},962786,700,2,"多选题","采用接地电阻仪测量接地装置的电阻值准备工作有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","将被测量电气设备断电",true,{"key":16,"text":17,"correct":14},"B","被测的接地装置应退出使用",{"key":19,"text":20,"correct":14},"C","断开接地装置的干线与支线的分接点",{"key":22,"text":23,"correct":24},"D","在距被测接地体10m和30m处，分别向大地打入两根金属棒作为樺辅助电极，并保证这两根辅助电极与接地体在一条直线上",false,{"key":26,"text":27,"correct":14},"E","测量接线处有氧化膜或锈蚀，要用砂纸打磨干净","ABCE","用接地电阻测量仪测量接地装置的电阻值，测量前的准备工作：a.将被测量的电气设备断电，被测的接地装置应退出使用。b.断开接地装置的干线与支线的分接点（断接卡子），如果测量接线处有氧化膜或锈蚀，要用砂纸打磨干净。c.在距被测接地体20m和40m处，分别向大地打入两根金属棒作为辅助电极，并保证这两根辅助电极与接地体在一条直线上。",{"id":6,"name":31,"category":32,"favorite":33},"基础知识（通用）","建筑工程",0]