[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959976":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},959976,699,1,"单选题","下列关于消防水泵接合器组件的安装顺序说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","接口、本体、连接管、止回阀、安全阀、放空阀、控制阀",true,{"key":16,"text":17,"correct":18},"B","接口、本体、连接管、止回阀、放空阀、控制阀、安全阀",false,{"key":20,"text":21,"correct":18},"C","接口、本体、连接管、止回阀、控制阀、安全阀、放空阀",{"key":23,"text":24,"correct":18},"D","接口、本体、连接管、安全阀、止回阀、放空阀、控制阀","消防水泵接合器一般应由接口、本体、连接管、止回阀、安全阀、放空阀、控制阀组成，结构设计应保证在使用后能够将消防接口到水流止回装置间的余水排尽。",{"id":6,"name":27,"category":28,"favorite":29},"初级技能","建筑工程",0]