[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959720":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},959720,695,1,"单选题","征地移民实施总工期应从工程建设开始前的第一期移民搬迁开始到( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程全部结束时为止",false,{"key":16,"text":17,"correct":14},"B","水库蓄水时为止",{"key":19,"text":20,"correct":21},"C","最后一期移民迁建完成为止",true,{"key":23,"text":24,"correct":14},"D","移民房舍全部建成时为止","",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]