[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959714":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},959714,695,1,"单选题","枢纽工程水库移民实施总进度应按枢纽工程截流、施工期度汛水位和水库蓄水(发电)计划、清库完成的时限等为控制点，根据移民工程建设的( )进行编制。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工进度",false,{"key":16,"text":17,"correct":14},"B","设计工期",{"key":19,"text":20,"correct":21},"C","合理工期",true,{"key":23,"text":24,"correct":14},"D","水库蓄水和分期移民计划","",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]