[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959709":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},959709,695,2,"多选题","生产安置人口的计算与( )有关。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人口构成",false,{"key":16,"text":17,"correct":18},"B","土地质量因素",true,{"key":20,"text":21,"correct":18},"C","统计年鉴面积",{"key":23,"text":24,"correct":14},"D","移民安置规划方案","BC","生产安置人口的计算，应考虑土地质量因素、统计年鉴面积与标准亩面积差别。B项，土地质量因素是同类型耕地地力不同的差异和不同类型耕地的差异，通过抽样调查，分析拟定修正系数，对涉及村、组被征地面积进行修正，计算生产安置人口。C项，统计年鉴土地面积与标准亩面积差异(即统计上报土地面积与实际面积的差异)的处理，可取若干个村或整组的耕地被征用的调查面积与统计年鉴面积对比，分析确定其修正系数，对涉及村、组的被征地面积进行修正，计算生产安置人口。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]