[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959701":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},959701,695,1,"单选题","移民安置规划的目标是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","规划设计基准年农村移民应达到的主要预期目标",false,{"key":16,"text":17,"correct":14},"B","使移民生活达到原有水平",{"key":19,"text":20,"correct":14},"C","达到移民搬迁年份的生活水平",{"key":22,"text":23,"correct":24},"D","规划设计水平年农村移民应达到的主要预期目标",true,"移民安置规划目标是指规划设计水平年农村移民应达到的主要预期目标。一般根据农村移民原有生活水平及收入构成，结合安置区的资源情况及其开发条件和社会经济发展计划，具体分析拟定。对于分期移民的工程，要制定分期目标值。一般由农村移民人均资源(主要为耕(园)地)占有量、人均年纯收入、人均粮食拥有量、居民点基础和公用设施应达到的基本指标(用地标准、供水、供电、内部道路和对外交通)及其他定量指标反映。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]