[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959655":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},959655,695,2,"多选题","枢纽工程水库移民实施总进度应按( )为控制点，根据移民工程建设的合理工期进行编制。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","枢纽工程截流",true,{"key":16,"text":17,"correct":14},"B","施工期度汛水位",{"key":19,"text":20,"correct":14},"C","水库蓄水(发电)计划",{"key":22,"text":23,"correct":24},"D","分期移民计划",false,"ABC","D项，移民搬迁和清库以及专业项目的迁(改)建，应根据水库蓄水和分期移民计划，按先低后高、先下游后上游、先淹先迁的原则实施。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]