[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959654":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},959654,695,1,"单选题","因兴建水利水电工程需要迁移的城镇，应当按照有关规定审批。按国家规定批准新建城镇扩大规模和提高标准的，其增加的投资，由( )解决。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","国家补偿",false,{"key":16,"text":17,"correct":18},"B","地方人民政府",true,{"key":20,"text":21,"correct":14},"C","个人投资",{"key":23,"text":24,"correct":14},"D","单位拨款","安置农村移民的居民点，迁建的城镇、集镇新址，复建或改建的专业项目(含企业和防护工程)，以规划设计成果为基础，按“原规模、原标准(等级)、恢复原功能”列入补偿投资(费用)概(估)算。结合迁建、复建、改建、防护以及企业技术改造、转产等原因提高标准或扩大规模所增加的投资，不列入补偿投资(费用)概(估)算。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]