[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959653":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},959653,695,2,"多选题","下列不列入水库征地移民补偿投资的有( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","因结合迁建提高标准或扩大规模所增加的投资",true,{"key":16,"text":17,"correct":14},"B","因防护以及企业技术改造提高标准或扩大规模所增加的投资",{"key":19,"text":20,"correct":14},"C","因转产等原因提高标准或扩大规模所增加的投资",{"key":22,"text":23,"correct":24},"D","以上说法都不正确",false,"ABC","安置移民的居民点，迁建的城镇、集镇新址，复建或改建的专业项目(含企业和防护工程)，以规划设计成果为基础，按“原规模、原标准(等级)、恢复原功能”列入补偿投资(费用)概(估)算。结合迁建、复建、改建、防护以及企业技术改造、转产等原因提高标准或扩大规模所增加的投资，不列入补偿投资(费用)概(估)算。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]