[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959634":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},959634,695,1,"单选题","规划设计基准年通常是指( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","征地移民搬迁结束年份",false,{"key":16,"text":17,"correct":14},"B","水库分期蓄水的年份",{"key":19,"text":20,"correct":14},"C","水库下闸蓄水的年份",{"key":22,"text":23,"correct":24},"D","编制规划设计的当年",true,"规划设计基准年是指编制规划设计的当年。规划设计水平年是指征地移民搬迁结束年份，对于水库是指水库下闸蓄水的年份。分期蓄水的水库，应以分期蓄水的年份，分别作为规划设计水平年。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]