[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959622":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},959622,695,1,"单选题","水利水电工程建设征地移民工作实行政府负责、投资包干、业主参与和( )的管理体制。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","综合监理",true,{"key":16,"text":17,"correct":18},"B","社会监督",false,{"key":20,"text":21,"correct":18},"C","群众监督",{"key":23,"text":24,"correct":18},"D","专业监理","目前，除地方政府行政体系的监督指导和审计检查外，水利水电工程移民安置实施工作还采用移民综合监理和监督评估两种社会监督形式。移民综合监理指对移民搬迁和安置实施过程中的进度、投资、质量进行现场全过程监督，并以监理报告形式向共同的委托方反馈意见，由上级移民机构督促移民实施主管部门对监理中发现的问题予以改正。移民监测评估则是阶段性对移民安置效果进行测评，以监测评估报告形式反映不同阶段发现的问题，报共同的委托方。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]