[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959587":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},959587,695,1,"单选题","关于专业项目恢复改建规划中正确的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","专业项目的恢复建设不列入水利水电工程补偿投资",false,{"key":16,"text":17,"correct":14},"B","无条件迁建恢复的专业项目，不予补偿",{"key":19,"text":20,"correct":21},"C","专业项目的迁建恢复应按“原规模、原标准(等级)、恢复原功能”的原则",true,{"key":23,"text":24,"correct":14},"D","专业项目应将扩大规模增加的投资列入水利水电工程补偿投资","专业项目处理包括受影响的铁路、公路、航运、电力、电信、广播电视、军事、水利水电设施(包括取水工程、水文站)，测量永久标志，农、林、牧、渔场，文物古迹，风景名胜区，自然保护区等。所有专业项目的恢复改建，均应按“原规模，原标准(等级)，恢复原功能”的原则进行规划设计，所需投资列入水利水电工程补偿投资。因扩大规模，提高标准(等级)或改变功能需要增加的投资，由有关单位自行解决，不列入水利水电工程补偿投资。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]