[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959548":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},959548,695,1,"单选题","按照国家有关基本建设程序管理的规定的项目审批制度，对于政府投资项目实行( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目核准制",false,{"key":16,"text":17,"correct":18},"B","项目审批制",true,{"key":20,"text":21,"correct":14},"C","项目审核制",{"key":23,"text":24,"correct":14},"D","项目备案制","按照国家有关基本建设程序管理的规定，根据《国务院关于投资体制改革的决定》(国发[2004]20号)确定的项目审批制度，项目依据投资主体、资金来源和项目性质，在项目立项审批阶段分别实行项目审批制、核准制、备案制。对于政府投资项目实行项目审批制。对于不使用政府投资建设的项目，区别不同情况实行核准制和备案制。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]