[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959543":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},959543,695,1,"单选题","不使用政府投资建设的项目，应区别不同情况实行不同的审批制度。实行( )的项目，仅需向政府提交项目申请报告。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","审批制",false,{"key":16,"text":17,"correct":14},"B","备案制",{"key":19,"text":20,"correct":21},"C","核准制",true,{"key":23,"text":24,"correct":14},"D","审核制","对于不使用政府投资建设的项目，区别不同情况实行核准制和备案制。凡列入《政府核准的投资项目目录》的项目，实行核准制，仅需向政府提交项目申请报告，政府对企业提交的项目申请报告，主要从维护经济安全、合理开发利用资源、保护生态环境、优化重大布局、保障公共利益、防止出现垄断等方面进行核准；对于《政府核准的投资项目目录》以外的企业投资项目，实行备案制，除国家另有规定外，由企业按照属地原则向地方政府投资主管部门备案。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]