[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959542":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},959542,695,2,"多选题","根据《水利工程建设程序管理暂行规定》(水利部水建[1998]16号)的规定，水利工程建设程序的阶段包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目建议书",true,{"key":16,"text":17,"correct":18},"B","立项决策",false,{"key":20,"text":21,"correct":14},"C","可行性研究",{"key":23,"text":24,"correct":14},"D","初步设计","ACD","根据《水利工程建设程序管理暂行规定》(水利部水建[1998]16号)，水利工程建设程序分为项目建议书、可行性研究、初步设计、施工准备(包括招标设计)、建设实施、生产准备、竣工验收、后评价等阶段。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]