[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959526":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},959526,695,2,"多选题","建设工程投标报价的依据包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","相关的法律法规",false,{"key":16,"text":17,"correct":18},"B","合同条件",true,{"key":20,"text":21,"correct":18},"C","拟采用的施工方案",{"key":23,"text":24,"correct":18},"D","工程材料、设备的价格及运费","BCD","建设工程投标报价的依据包括：①招标文件(包括对技术、质量和工期的要求)；②设计图纸、设计文件及说明、工程量清单等；③合同条件，包括词语含义、合同文件、双方的一般责任、施工组织设计和工期、质量标准、合同价款与支付、材料设备供应、设计变更、竣工与结算等内容；④现行建设预算定额或概算定额、单位估价表及取费标准等；⑤)拟采用的施工方案、进度计划；⑥工程材料、设备的价格及运费；⑦现场施工条件；⑧本企业施工组织管理水平、施工技术力量、设备装备能力等；⑨本企业过去同类工程施工成本数据。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]