[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959517":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},959517,695,2,"多选题","水利工程建设项目招标前，向水行政主管部门备案的招标报告具体内容应当包括( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","招标方式",true,{"key":16,"text":17,"correct":14},"B","分标方案",{"key":19,"text":20,"correct":21},"C","招标所需费用",false,{"key":23,"text":24,"correct":14},"D","评标方法","ABD","水利工程建设项目招标前，按项目管理权限向水行政主管部门提交招标报告备案。报告具体内容应当包括：招标已具备的条件、招标方式、分标方案、招标计划安排、投标人资质(资格)条件、评标方法、评标委员会组建方案以及开标、评标的工作具体安排等。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]