[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959511":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},959511,695,2,"多选题","项目动态管理计算机信息系统由( )组成。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","信息源",true,{"key":16,"text":17,"correct":14},"B","信息获取",{"key":19,"text":20,"correct":14},"C","信息处理和存储",{"key":22,"text":23,"correct":24},"D","信息传递",false,"ABC","项目动态管理计算机信息系统是以计算机为手段，采集、存储和处理相关信息，为建设项目组织、规划和决策提供各种信息服务的计算机辅助管理系统。它由信息源、信息获取、信息处理和存储、信息接收以及信息反馈等环节组成。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]