[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959505":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},959505,695,1,"单选题","项目立项审批对于以投资补助和贴息方式使用中央预算内资金不超过2亿元但超过3000万元且占项目总投资比例超过( )％的项目，由国家发展和改革委员会审批可行性研究报告。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","30",false,{"key":16,"text":17,"correct":14},"B","40",{"key":19,"text":20,"correct":21},"C","50",true,{"key":23,"text":24,"correct":14},"D","60","项目立项审批对于政府投资项目实行项目审批制。对于采用直接投资和资本金注入方式的项目，从投资决策角度只审批项目建议书、可行性研究报告，除特殊情况外不审批开工报告，同时严格初步设计和概算审批工作；对于以投资补助和贴息方式管理的项目，只审批资金申请报告。但以投资补助和贴息方式使用中央预算内资金超过2亿元或不超过2亿元但超过3000万元且占项目总投资比例超过50％的项目，按直接投资或资本金注入方式管理，由国家发展和改革委员会审批可行性研究报告。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]