[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959457":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},959457,695,2,"多选题","水土保持方案编制的“三同时”原则包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","水土保持工程与主体工程同时设计",true,{"key":16,"text":17,"correct":14},"B","同时施工、同时投产使用",{"key":19,"text":20,"correct":14},"C","项目竣工验收时同时验收",{"key":22,"text":23,"correct":24},"D","水土保持工程与主体工程同时进行后评价",false,"ABC","《中华人民共和国水土保持法》第十九条规定：“建设项目中的水土保持设施，必须与主体工程同时设计、同时施工、同时投产使用。建设工程竣工验收时，应当同时验收水土保持设施，并有水行政主管部门参加。”",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]