[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959433":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},959433,695,2,"多选题","开发建设项目水土保持概(估)算与水土保持生态建设概(估)算的人工工资及基础单价编制方法和计算标准的区别有( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","人工工资计算方法及标准不同",true,{"key":16,"text":17,"correct":14},"B","材料采购及保管费率不同",{"key":19,"text":20,"correct":14},"C","电、水、风单价计算方法不同",{"key":22,"text":23,"correct":24},"D","水土保持生态建设增加了征地及淹没补偿费",false,"ABC","开发建设项目水土保持概(估)算与水土保持生态建设概(估)算的人工工资及基础单价编制方法和计算标准的区别：①人工工资计算方法及标准不同；②材料预算价格编制方法基本相同，但采购及保管费率不同；③电、水、风单价计算方法不同。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]