[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959422":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},959422,695,2,"多选题","水土保持工程措施主要由3个部分组成，即( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","坡面治理工程措施",true,{"key":16,"text":17,"correct":18},"B","泥石流治理工程措施",false,{"key":20,"text":21,"correct":14},"C","沟谷治理工程措施",{"key":23,"text":24,"correct":14},"D","小型蓄排引水工程措施","ACD","水土保持生态建设工程措施一般可分坡面治理工程、山沟治理工程、山洪排导工程和小型蓄水用水工程。",{"id":6,"name":28,"category":29,"favorite":30},"专业知识（水利水电）","建筑工程",0]