[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959385":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},959385,695,1,"单选题","土质防渗体分区坝预留沉降量一般为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","坝高的1%",true,{"key":16,"text":17,"correct":18},"B","坝高的1.5%",false,{"key":20,"text":21,"correct":18},"C","坝高的2%",{"key":23,"text":24,"correct":18},"D","坝高的3%","土石坝坝基(包括坝头，下同)处理应满足渗流控制(包括渗透稳定和控制渗流量)、静力和动力稳定、允许沉降量和不均匀沉降量等方面要求，保证坝的安全运行。处理的标准与要求应根据具体情况在设计中确定。竣工后的坝顶沉降量不宜大于坝高的1％。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]