[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959332":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},959332,695,1,"单选题","水电站进水建筑物的进口流速一般控制在( )左右。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.5ms",false,{"key":16,"text":17,"correct":18},"B","1.5ms",true,{"key":20,"text":21,"correct":14},"C","1.2ms",{"key":23,"text":24,"correct":14},"D","1.0ms","水电站进水建筑物的进口段横断面一般为矩形，可为单孔或双孔。进口流速不宜太大，一般控制在1.5ms左右。进水口拦污栅的平均过栅流速一般取0.8～1.0ms。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]