[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959330":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},959330,695,1,"单选题","对拱坝坝基进行全面固结灌浆时，固结灌浆孔的孔距、排距一般为，固结灌浆孔的孔深宜采用。( )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2～4m、4～8m",false,{"key":16,"text":17,"correct":14},"B","2～5m、5～8m",{"key":19,"text":20,"correct":14},"C","2～5m、4～6m",{"key":22,"text":23,"correct":24},"D","2～4m、5～8m",true,"一般要求对拱坝坝基进行全面的固结灌浆，断层破碎带及其两侧影响带应加强固结灌浆。固结灌浆孔的孔距、排距一般为2～4m，固结灌浆孔的孔深宜采用5～8m。固结灌浆孔宜布置成梅花形。灌浆孔方向应根据主要裂隙产状，穿过较多的裂隙。灌浆压力在保证不掀动岩石的情况下，宜采用较大值，一般为0.2～0.4MPa，有混凝土盖重时，可取0.3～0.7MPa。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]