[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959264":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},959264,695,1,"单选题","险工段的坝式护岸顶部应( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","高于枯水位0.5m以上",false,{"key":16,"text":17,"correct":14},"B","超过正常运用水位0.5m以上",{"key":19,"text":20,"correct":21},"C","超过设计洪水位0.5m以上",true,{"key":23,"text":24,"correct":14},"D","高于非常运用水位0.5m以上","堤岸顶部的防护范围包括：①险工段的坝式护岸顶部应超过设计洪水位0.5m及以上；②堤前有窄滩的防护工程顶部应与滩面相平或略高于滩面。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]