[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-959172":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":24,"analysis":25},959172,695,2,"多选题","溢流重力坝常用的消能方式有( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","底流式消能",true,{"key":16,"text":17,"correct":14},"B","挑流式消能",{"key":19,"text":20,"correct":14},"C","面流式消能",{"key":22,"text":23,"correct":14},"D","消力戽","ABCD","泄水建筑物的下游应设置相应的消能防冲设施，避免过坝水流对下游河床冲刷危及枢纽建筑物和岸坡的安全。通常采用的消能方式有挑流、跌流、底流、戽流等。",{"id":6,"name":27,"category":28,"favorite":29},"专业知识（水利水电）","建筑工程",0]